The Global Water Initiative (GWI) was an action-research and advocacy programme that ran from 2008-17. The project is now closed. This site is no longer being updated, but allows access to GWI outputs until 1 October 2020 when it will also close. After that date, information about the project and core GWI technical publications will continue to be available from the IIED website and Publications Library.

  • English
  • Français

Resettlement, compensation and rights of local populations in the area of the Taoussa dam (Mali)

Resettlement, compensation and rights of local populations in the area of the Taoussa dam (Mali)
Document language: 
French

Author(s): 
Moussa Djiré, Amadou Keita, Kadari Traoré

This study, conducted on the conditions of populations displaced by Taoussa development project, intends to analyze the nature of the "social contract" between the state and local communities around the dam. The material terms and the legal framework for their resettlement will be analyzed, firstly, to assess their effectiveness, achievements and limits to feed into the debate on benefit-sharing around dams and, secondly to formulate recommendations to influence the process in the interest of all parties.

The Taoussa project is one of the major development projects underway in Mali. Located in the Gao region, it has various components including the construction of a dam that will, according to its designers, create a reservoir with a large capacity to maintain a low flow that will promote regeneration of the Niger river ecosystems and the sustainability of socio-economic activities.

The study focused particularly on the level of information received by local actors, their participation in various phases and their appreciations and expectations of the project.

Date: 
December 2010